Oklahoma Data Center Projects
Projects by status
| Operational |
|
Pryor, Mayes County |
Rural & Other Counties |
8 data center buildings |
— |
Oklahoma's original hyperscale anchor; online since 2007, still expanding. |
| Operational |
Cerebras Systems Cerebras Oklahoma |
Oklahoma City |
OKC Metro |
10 MW |
— |
AI compute facility. |
| Operational |
Cogent Cogent Data Center |
Oklahoma City |
OKC Metro |
5,294 sq ft |
— |
— |
| Operational |
Lumen Oklahoma City 1 |
Oklahoma City |
OKC Metro |
— |
— |
— |
| Operational |
MIDCON Recovery Solutions MIDCON Data Center |
Oklahoma City |
OKC Metro |
60,000 sq ft |
— |
— |
| Operational |
RACK59 RACK59 Oklahoma City |
Oklahoma City |
OKC Metro |
30,000 sq ft |
— |
— |
| Operational |
TierPoint Oklahoma City 1 & 2 |
Oklahoma City |
OKC Metro |
— |
— |
— |
| Operational |
ValorC3 ValorC3 Oklahoma City |
Oklahoma City |
OKC Metro |
65,000 sq ft |
— |
— |
| Operational |
Windstream Downtown OKC |
Oklahoma City |
OKC Metro |
— |
— |
— |
| Operational |
HP (Hewlett Packard) Cherokee Data Center |
Tulsa |
Tulsa Metro |
430,000 sq ft |
— |
— |
| Operational |
Isocentric Networks Downtown Tulsa |
Tulsa |
Tulsa Metro |
— |
— |
— |
| Operational |
Jackson Technical Tulsa facility |
Tulsa |
Tulsa Metro |
— |
— |
— |
| Operational |
Lumen Tulsa 1 |
Tulsa |
Tulsa Metro |
— |
— |
— |
| Operational |
OCOSA OCOSA Data Center |
Tulsa |
Tulsa Metro |
— |
— |
— |
| Operational |
Kanbar Properties Philcade Data Center |
Tulsa |
Tulsa Metro |
— |
— |
Historic Philcade Building retrofit. |
| Operational |
TierPoint State Farm / Archer |
Tulsa |
Tulsa Metro |
— |
— |
— |
| Operational |
Facility Gateway Tulsa Technology Exchange |
Tulsa |
Tulsa Metro |
— |
— |
— |
| Operational |
TulsaConnect DC-3 & DC-5 |
Tulsa |
Tulsa Metro |
— |
— |
— |
| Operational |
CORE Data Center CORE Data Center |
Vinita |
Rural & Other Counties |
5,000 sq ft |
— |
— |
| Under Construction |
Core Scientific Muskogee HPC Data Center |
Muskogee |
Rural & Other Counties |
100 MW |
— |
2026 completion target. |
| Under Construction |
Core Scientific Second Muskogee facility |
Muskogee |
Rural & Other Counties |
— |
— |
— |
| Under Construction |
CloudBurst OKC Campus |
Oklahoma City |
OKC Metro |
200 MW |
— |
Construction affected by a local moratorium. |
| Under Construction |
Google & Beale Infrastructure Project Clydesdale |
Owasso, Tulsa County |
Tulsa Metro |
506 acres |
$15B+ (cumulative) |
Broke ground late 2025; Google confirmed as the end user. |
| Planned |
|
Muskogee County |
Rural & Other Counties |
2 campuses |
$9B |
Early development. |
| Planned |
|
Stillwater |
Rural & Other Counties |
~400 acres, 6 buildings |
~$3B |
Early development. |
| Planned |
American Tower EDC Oklahoma |
Oklahoma City |
OKC Metro |
4 MW capacity |
— |
— |
| Planned |
Beale Infrastructure Project Mustang |
Claremore |
Rural & Other Counties |
Multiple buildings |
— |
City signed NDA with developer Feb. 2024, disclosed Jan. 2026. |
| Planned |
Buckley Bros Holdings Pawhuska AI Data Center |
Pawhuska |
Rural & Other Counties |
8–10 MW |
— |
— |
| Planned |
Undisclosed developer Regional Data Center |
Pittsburg / Atoka County |
Rural & Other Counties |
— |
— |
2027–2029 build timeline reported. |
| Planned |
Meta Project Anthem |
East Tulsa |
Tulsa Metro |
~340 acres |
$1B+ |
Near Fair Oaks Industrial Park. |
| Planned |
Beltline (Beltline Energy) Yukon project (reported as "Gamma Resources" in some coverage) |
Yukon |
OKC Metro |
— |
— |
City signed NDA May 2025; zoning deferred twice; near Redbud power plant. |
| Planned |
Aligned Data Centers Amber campus |
Amber, Grady County |
Rural & Other Counties |
— |
— |
Land acquired; first landowner meeting held Aug. 10, 2026. |
| Contested / In Limbo |
|
Sand Springs |
Tulsa Metro |
827 acres |
— |
Annexed without landowner notice; conservation-easement dispute; 3 lawsuits filed. |
| Canceled |
Undisclosed developer Broken Arrow proposal |
Broken Arrow |
Tulsa Metro |
— |
— |
— |
| Canceled |
Beale Infrastructure Project Atlas |
Coweta |
Tulsa Metro |
— |
— |
Scrapped after community opposition; NDA disclosed Oct. 2025. |
| Canceled |
Boomtown Manufacturing Lawton site (CLO school land) |
Lawton |
Rural & Other Counties |
388 acres |
100–500 MW capacity |
Lease canceled Dec. 2025 after repeated state commission delays. |